It seems very distant to be providing this update from the UK. For the input I must thank Collin and Jim.
The immediate good news was that apparently we did not put Ethan and Evelina off. Both were back and hard at work on Saturday.
On 1630:
· Rick, Ed & Collin concentrated on lagging the back head. First, the pieces of sheet metal were fitted up against the firebox to determine where and how they fit together. After having accomplished that step it was determined that the firebox door should be added next as it serves as a template against which the insulation is cut.
The previous week the fire door casting, weighing several hundred pounds, was lifted into the tank's coal bunker with the forklift. A team including Rick, Collin, and Eric dragged the door over to the stoker coal feed pipe and placed it so the mating flange to the backhead was horizontal. Rick then mixed up the special fire-resistant concrete and mudded the flange. This mud serves as the gasket between the fire door and the back head where traditional insulation would be consumed by the fire. This is a tricky operation as the concrete has to conform to the surface of the back head before setting up yet be solid enough that it does not fall out of the flange once the flange is vertical.
On the initial attempt the mixture was not set up enough so the acetylene rig was brought over to heat up the flange and speed up the drying process. Then a paper was tied to the top of the flange to hold the concrete in place until the fire door casting could be bolted to the back head. Once in place and torqued down, Rick mudded the flange interface completing the seal against the back head.
As a final step to the back head project, Rick & Collin determined the appropriate width of the insulation for the back head is 2". Since our insulation comes in 2 1/2" sheets, Rick ripped down the sheets, one at a time and then cut them down the center as well. So, when work resumes next week, the back head insulation work can proceed as all parts are now ready.
On Sunday, Tom and Cameron worked on aligning the fire-hole door casting with the stoker riser so that the securing bolts can be fitted.
· Work progressed steadily on the boiler insulation as well. Eric, Jerry, Ethan, Evelina, Brian and Jim continued lagging the boiler courses. Since Eric has led this project and we had several new volunteers Eric became known simply as "Crew Chief". In totality, the lagging blocks are in place on the first, second and much of the third courses with a significant portion of the infill mudding also accomplished in these areas.
· Jim Opolony picked up, from the wood shop, the cab window frame that Collin put his shoulder through two weeks ago. Many thanks to Bob and the guys for their efforts in producing the beading. Ed worked on the frame, cleaning it up and preparing it for the installation of the glass.
· Dennis worked on the sheet metal for the smokebox. A number of the pieces were cut to shape and checked against the old damaged sections to ensure a match.
· Tom and Ralph worked on the throttle.
· Mike and Brian continued work on the valves of the air compressor.
In other areas:
· Phil and several others worked on preparing the steam locomotives on steam row for movement. More heavy duty switching is in prospect!.
· Stu and Jane worked on the planer and have now primed the main pillar
So it sounds like another successful weekend..
Nigel
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]