It was a good day for working inside the shop !. Temperatures outside discouraged anything but
limited activity.
On 1630 steady progress was made on the work list:
·
Rick completed screwing the sheet metal section
around the radius of the backhead. He
has now moved on to making and fitting some additional sheet metal against the
front sheet of the cab, where there was a gap that exposed some insulation;
·
I removed the injector overflow (coal and
footplate spray hose), which was leaking dangerously during test running. The fittings have all been cleaned and
refitted. All we now need is a length of
new hose;
·
Ralph managed to remove the steam line to the blower,
remade the joint that was noted as leaking under steam pressure, then refitted
the whole assembly. So that issue should
now be fixed;
·
Collin and Ralph then removed the two injector
steam lines. These are large copper
pipes that need to be annealed periodically.
So we will do this and then renew the insulation that is wrapped around
them;
·
Jerry worked on the insulation along the
boiler. This is a slow and tricky job as
we need to close all the small gaps in the sheet metal that could allow water
to get in when the loco is outside in heavy rain. He has made good progress on making the
firebox sided cladding sheets, where the insulation is attached to the sheet
metal. In this shot you can also see
where the injector steam pipes were removed.
This also clearly shows the reason for different way of lagging this
area. The exposed heads, that can be
seen where the cladding is still missing, are rigid stays with tell-tale
holes. These must be checked annually,
hence the need to remove the sheet metal and lagging frequently.
He also located and test fitted some
special strips of banding that close the gap against the front sheet of the
cab. We had wondered why we had such a
large gap there until he found the missing strips !!;
·
Phil, with Evelina and Eddie, spent a dirty and
unpleasant morning in the firebox. They
managed to match the fire bricks to the gaps between the arch tubes, where they
form the brick arch, and produce a diagram that tells us exactly how many
bricks of each of the 5 types we need to build the arch;
·
We then made a cold trip to the service box car
and found the spares we needed to have a complete set in the firebox ready to
build the arch. Phil and I then checked
the Milwaukee box car out in yard 13.
This confirmed that we have large stocks of 4 types of brick (which came
from Eagle Pitcher in the 1970’s) but need to make a pattern for the smallest
ones which fit over the arch tubes against the tube sheet;
·
Jane painted the straps that secure the air
tanks. Phil and I set up the cylinder
front covers ready for her to paint so that these will be ready for fitting
once Tom has completed measurement of the valve chambers;
·
Evelina worked with Dennis on wire brushing the
tender coal space so that he can weld some strengthening steel in weak spots around
the stoker motor;
·
I reassembled the hydro test pump with the new high
pressure hose so that the equalizing reservoir can be tested next weekend..
On the Shay
·
Phil worked with Dennis on fitting the last of
the spring locating plugs into the bolster;
·
Ralph and I relocated all the components of the drive
shaft onto a pallet under the locomotive and I started to degrease these ready
for refitting;
On 428
·
Cameron completed machining the wedges;
·
One of the axles was hoisted so that accurate
measurements of diameter could be obtained.
This proved very satisfactory.
The tires have ample thickness to allow them to be re-profiled.
Around the shop
·
Jane made good progress in stripping old paint
from the large press in preparation for painting;
·
Bob continued testing the planer.
So a typical and productive Winter workday in the steam
shop.
Nigel
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...