Thursday, December 13. 2012Wood Shop Update - December 12, 2012For several of the last few years, we have had a tradition of a pot luck volunteer Christmas Party. If has grown from a handful of folks to a larger and larger group every year, many departments attending, and sharing good cheer. I bet there were over 45 attending this year. So without further ado MERRY CHRISTMAS Just as the party grows larger, so does the work of setting up the wood shop, putting away the projects, and a substantial cleanup. A big thanks goes out to all the committee members and helpers, especially Pete Galayda (shown here) and his wife Jan. "Go to the dust collector and take a left." There were ample food dishes and deserts to sample and no one went hungry. It was set up buffet style and a long line quickly formed. But that does not mean no work was done. Before the serving started, Jim Leonard and Dave Rogan were prime painting the three new windows for our CGW X 38 snowplow. We finished the woodworking on them last week and they gathered little dust. After lunch, they were dry enough to flip over and the other side is also prime painted. The wood shop serves all and any department and all types of work. John Faulhaber is leading the way to make a lot of new material for the Lake Shore Electric 810 traction freight trailer. We selected and purchased the lumber a few weeks ago and here John is doing the layout work on a large plank, destined to become new tack molding. There is enough stock to also make almost 350 linear feet of specially profiled tongue and groove pieces for the roof. Dave Rogan and John Faulhaber start the process by creating a straight and true edge on each piece, running them through our jointer. Jeff Brady is in the background working on new sheet metal window post caps for Michigan Electric 28. After jointing and ripping several pieces, the crew here is doing the profile work for a drip lip. Jim Leonard, Dave Rogan, and john Faulhaber have set up the saw and are guiding the twelve foot long pieces through the process. That is longer stock than we usually process, but we want to minimize the number of joints on this stock when installed on the car. We made 96 feet of material, sanded it and Jim got primer on one side before leaving for the day. Not bad production for an afternoon when everyone had a full belly and wanted a siesta more than anything else! Henry Vincent is far enough along restoring separate parts for the new table saw, that he was able to apply some shop green finish paint. Jon Fenlaciki has been working to restore a window for Indiana Railroad 65. Now in the final stages of glazing, I am confident it will soon resume to its rightful place on the car. Tuesday, December 11. 2012Connector track electrifiedTrolley wire has been installed on the connector track. This allows electric operation from barns/yards 6, 7 and 8 directly to South Junction and the carline. The zig zag moves using the tail track and crossing the Carline at the diamond with the movement against normal traffic flow can all be avoided. I know it may appear that nothing is getting done in D/C line, that is because often the work being done is invisible to the visitor. Parts need to be reconditioned. Budgets are better than what they were 30 years ago but these projects are expensive. I am running out of some parts. Projects like this one take several budget-years to accumulate materials before anything tangeble can be seen. The volunteers are spread so thin now days that I am usually working alone. I hope this "bloging" will encourage some new volunteers to A/C-D/C line. I am proud of what I get done here. Come join me. You don't need an appointment... just show up. New anchors, down guys and frog pulloffs at Central Ave. This is the main anchorage for wire in yards 7,8 and connector track. I began work on this project over two years ago when poles were set and guy anchors installed. Completion of the connector track overhead directly effects improvements to the mess of loose overhead in yards 6,7 and 8. It's all a big spiderweb of span wire, most of it not properly served. The yards 6,7,8 project is another story. Those yards are already much improved by the replacement of rotten poles and installation of several new tight cross spans. Several of these cross spans support wire on the connector track and all three yards. New anchors, down guys and several frog pulloffs were installed North of Central Ave allowing the wire in all three yards and connector track to be pulled up tight. This also straightened the "groink" in the trolley bus line at the crossing. Good tight overhead wire starts with solid anchorage. That, has been a problem. In the early days of IRM we had to "make do" with whatever materials we could procure. This often meant not too rusty second hand parts, old but still sound poles and crossarms. Occasionally, our friends at the local electric utility would "lose hardware" in the field or "clean" the storeroom and we would get some good stuff. Often we had to make do with smaller or less hefty material than what was preferred Materials we couldn't get for free we had to buy with the little money we had. We bought cheaper materials, the smallest that would do the job. Combined that with a lack of experience and you get guy anchors creeping out of the ground over time, down guys getting loose, used poles rotting. Those practices in the past resulted in loose sagging overhead today. Fortunately, thanks to our visitors and supporters IRM has grown to the point where we can afford to buy the right materials and with our dedicated volunteer we can begin fixing the problem areas. The first part of the project involved providing a good anchorage. Over a couple of years new 30 and 35 foot class 4 wood poles were purchased and installed. Some were replacing rotted poles along the South side of yard 8. Wherever poles were replaced that required guying, new anchors and down guys were also installed. The typical guy installation consists of a 4" square curved washer, 3/4" machine bolt, a guy hook (hog ear) with lag, 5/16" EHS galvanized guy wire, 1 porcelain strain insulator(johnney ball), 5/8"x7' anchor rod with thimbleye nut and a single 8" anchor helix. Attachment to the anchor is made with 2 three bolt clamps( this allows future adjustment). Attachment to the hog ear and johnney ball are made with preformed deadends. Normally, guy and span wire attachments to insulators and hardware,here at IRM, are made by the serving method using softer Siemens Martin grade wire. This is in keeping with our desire to maintain a historical motife. Experience has shown that down guys here at IRM are subject to such abuse that the strength of EHS wire is necessary. EHS wire is too stiff to be served so, preformed deadends or guy clamps are used. A fullround steel guy guard is attached at the ground end to both protect the guy from damage and make the guy wire more visible to pedestrians. At the South end of the track was a slight curve. Span wire was installed between three poles on the outside of the curve this is the "backbone" for pulloffs which guide the trolley wire around the curve. Four bracket arms were installed on the new 35 foot poles. 4/0 grooved hard drawn copper trolley wire was pulled in and tied off. A new trolley frog and section insulator were cut in on the carline at the South end of the first "S" curve. The new trolley wire was deadended on the section insulator. Now the new trolley wire could be pulled up close to sag and tied off at the North end. Before the wire could be brought up to full tension, the pulloffs on the curve had to be installed and pulled up to near final position. Also, the track 83 trolley frog had to be removed so that a section of the track 84 wire could be unspliced and swung over to the connector track. Doing this would avoid having to make several splices. With the former track 84 wire over the connector track, the new wire could be sucked up to final sag and spliced together thus energizing the new wire. Next the pulloffs on the curve were adjusted to their final position and all spans were served up permanent. The last thing to do was clip the tangent poles allowing the track to be put into service.
Sunday, December 9. 2012
Covered space for steam collection Posted by Nigel Bennett
in Steam Department at
16:12
Comments (0) Covered space for steam collectionIn parallel with bringing #1630 back into operation we urgently need to improve the storage of our non operating steam locomotives. Many of our locomotives are currently stored outside where they are deteriorating. As detailed on the Illinois Railway Museum main website, the museum is currently planning an additional covered storage area. Space in this building will be provided based upon the cost of the building, which works out at about $215 per foot length. This is a substantial cost for a large steam locomotive which can be about 100 feet in length. Some of our best examples, notably the Burlington Hudson #3007, do not have dedicated covered track space. (While it is currently under cover it is occupying general department space and would potentially have to be put outside again when we have locomotives in operation). Other items that we would dearly like to get under cover, where they could be cosmetically restored for better display, are the Rock Island 4-6-2 #938 and C&O 2-8-4 #2707. Please consider donating to the fund raising for barn #14 nominating the steam department. As an added incentive, we have a number of the "Burlington Bulletin" books on the S-4 Hudsons including #3007, which we will provide to anyone who can donate $25 or more to the steam department for covered space. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]