It was a week of very hard work leading to a huge milestone.
As described last week, we had reached the frustrating point
of chasing leaks around the tube ends and a small check list of other minor
issues requiring correction in order to get the boiler fit for the formal hydro
test.
Brian Davies is staying at Union for three weeks to help
with the work and he put in long hours with some of us who were able to spend a
day at Union during the week. Several
important tasks were achieved. With
Jason, he was able to largely complete the cleaning and checking of the air brake
valves.
However the key focus was the boiler. As the number of leaking tubes decreased,
they became more frustrating and more inclined to cause an adjacent tube to
leak when you rolled them. The final
session on Saturday had many of us involved during the day and lasted until 11 at night but by the
end, we were down to one super heater flue that has a small leak around it that
we expect will seal itself when the boiler is fully heated, although it drips
very slowly under hydro pressure.
So, Brian, Jim and I were back in the shop at 8:30 on Sunday,
unfortunately not to assist with the last day of Thomas but to meet with the
FRA inspector for the formal hydro test.
I am glad to say that the old lady passed !. Aside from the tube end and a few drips from
tri-cocks and blow down valves she held pressure very well with no sign of
leakage.
So Saturday was rather a frustrating day. Very little on 1630, aside from the tubes,
could be worked on until the hydro was completed.
Cameron and Phil worked with Tom on the bolster for the
Shay.
Richard and Ed continued to work on preparing the cladding
for lagging in the cab.
Bob finally received a suitable breaker to link the planer
into the supply panel. So he was able to
continue work on running power to the planer.
However on Sunday, after the test, a great deal of work
opened up.
The tubes can now be beaded so, in preparation for that, I
spent quite a while in the smokebox grinding tube ends to the exact 1/4 inch
required to form good bead. Later Brian took over and, by the time that I
left, we were close to the point where he can bead all flues and tubes in the
smokebox that are to be beaded. Ideally
we want to get this done in the next couple of days so that the beaded tubes
can be tested for leaks by Wednesday.
On Wednesday we hope to take off the dome cover, drain the
boiler and start drying it out so that the inspector can carry out the internal
inspection on Friday. This is a Federal
requirement. When a boiler has been over
pressured, as it is for the formal hydro test, it must be inspected to ensure
that nothing internal, such as the brace attachments, has been damaged or
loosened. After this, any pressure
testing is strictly limited to boiler pressure (180 psi). If any pressure beyond this is applied a
further internal inspection is required.
Beading of the smokebox end is essential before a lot of
work starting with refitting the super heater elements and then moving on to the
rest of the smokebox equipment can be undertaken.
In the cab, work will now start on lagging the firebox and
fitting the cladding so that all the controls can be finally refitted. With the hydro complete, we can now start
covering the boiler again. Up until
today, none of this could be started as a clear view of all the surfaces of the
boiler was required for the inspection.
In the firebox, Jerry applied the protective paint to the
patch and rivets below where the grates will fit. Once this is dry, the grates that have been
removed while we worked on the patch, will be refitted.
One key thing about the milestone today is that, while she
may currently look less complete than she did in 2011, we have actually passed
the key inspection step for which we were preparing in Spring 2011 when we hit
the problem with the firebox.
So overall a very successful week. While not too much visible has changed, but we
have removed the barrier to a whole lot of tasks that will make 1630 look much
more like an operating locomotive again in the next month.
Nigel
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]