Comments (14) Steam Department Update 07-27-2013This was a big day at the steam shop. All activity was focused on 1630 and the first testing of the boiler completely full of water and under some pressure.
It is a fairly lengthy process to set the boiler up for pressure testing. The boiler and water need to be fairly warm (about 100 F) for testing. So aside, from pumping 2500 gallons of water from the milk car to the boiler, there is about 5 hours of circulating the water thru the gas fired pool heater to bring the whole system up to an even temperature.
Starting in the morning it was late afternoon before the whole system was at temperature. During that time we spotted and corrected minor leaks around the inspection and dome covers.
Removing the dome cover to fix the seal gave this interesting shot into the open dome. The boiler is now about as full of water as it can be.
With everything sealed we started to apply pressure to check for leaks. In general, we were fairly pleased with the way that the work we have done stood up to pressure. There were maybe 20 small to tiny leaks disclosed around tube ends. In retrospect one mistake was that we did not fix leaks around two super heater flues in the front tube sheet. These were very small sources of drips under gravity but became the limiting factor when we reached 150 psi.
The firebox patch was tight aside from a small spot in the caulked joint with the mud ring which showed a slight leak at 150 psi. This should be easily fixed by a little more caulking. A couple of rivets close to the patch showed signs of weeping. This is not surprising given the expansion and contraction associated with the welding and can be fixed by a little work with the caulking hammer.
The nuisance and minor setback was an area that we had not worked on. We found tiny pinhole cracks in the sockets of two flexible stays in the back head. These may have been there when she last ran as they are so small that we would probably not have seen any leakage from under the lagging and jacket. Certainly they would not have caused any loss of pressure in the hydro-testing.
However, knowing that they are cracked, even a pinhole, they must be replaced. This involves grinding off the inner end of the stay and, after heating the end of the stay, trying to unscrew the stay from the socket. If this fails you have the much more time consuming job of drilling out the stay at the inner end. However, it worked well. By Saturday evening both stay bolts were out, without the need to drill either. In this view you can see the empty sockets after the stays were removed.
On Sunday I started cutting one of the sockets off from the back head and, in the afternoon, Mike and Tom completed the job. So both of the sockets shown above are now gone and we are ready to fit the new sockets. Tom will then need to drill and thread two new stay bolts so they can be refitted. This will mean no pressure testing next weekend but hopefully all will be back and the leaks fixed by 8/10.
On this basis, I met with the FRA inspector on site Sunday and we scheduled the formal hydro test for 8/18, subject to a successful second stage test for leaks the previous weekend.
Just about all effort was concentrated on 1630. However, a big event was that both Bill Chyna and Glenn Parkhurst visited. Glenn for the first time since his motor cycle accident in May. Glad to say they were both in good form and Glenn is hoping to be able to join us again when he has his prostheses fitted in the next few months.
I am heading for the UK on business this week and will not be around the shop next weekend. So I am hoping to see a lot of progress when I get back in two weeks time !.
Nigel
Sunday, July 21. 2013
Steam Department Update 07-20-2013 Posted by Nigel Bennett
in Steam Department at
21:55
Comments (5) Steam Department Update 07-20-2013
It has been a really busy week for me at the museum hence a
rather late blog update!!.
I spent Wednesday at the steam shop with Phil and Ed. The main focus was on sealing all significant leaks at the tube ends that showed when the boiler was filled with water. By end of Wednesday we were to the point that , when filled well above the crown sheet, we had only minor dribbles and drips.
Saturday was a normal and fairly successful work day at the shop and Sunday I spent working with the Jim West and the Operations Department on switching for the Diesel Days event. So the blog is a little late this week !.
So what happened Saturday at the steam shop?. Overall a great deal was achieved although there was one set back which meant that we were not able to get as far as our most ambitious targets.
On 1630 I guess I had better try to answer one question I was asked a lot at the event on Sunday - when will you be hydro-testing the boiler?. The answer has to depend upon what exactly you mean by hydro-testing. As the pre-requisite for moving on the steam testing we must demonstrate that the boiler can be pressured using heated water to 125% of operating pressure (so 225 p.s.i. in our case) and sustain that pressure with minimal leakage for a period. Our current expectation is to reach that point in about 3 weeks. However our path to that involves using water, at first simply filling the boiler, then applying increasing pressure to identify and test the correction of any leakage. This is the process that we are currently following. On Saturday our objective was to finally seal any leakage at the tube ends on simply filling the boiler and then seal the boiler to allow some pressure to be applied.
· Following on from the work that Phil and I did on Wednesday, a team including Phil, Collin, Eric and Sean took it in turns to identify and seal the last little leaks that showed by carefully rolling the identified tube ends slightly more. This was hard and tedious work but, by early afternoon, the tube ends appeared to be dry with the boiler full of water.
· Dennis annealed the copper sealing rings for the two covers.
· In parallel with this one team worked on cleaning the threads of the studs that attach the dome cover and another on fitting the cover of the inspection hatch. These are the last two components required to seal the boiler and allow pressure to be applied.
· All seemed to be going well until one of the studs securing the inspection hatch sheared off during tightening.
Luckily everything seems to be shaping up well on replacing the stud. Dennis was in the shop and did a great job of welding a nut onto the broken stud and, to our great relief, this stood up to several of us pulling on a large wrench and the stud unscrewed from the seating. In this view you can see the broken stud with the nut welded onto it.
This was very good news as the alternative, had it failed to extract, would have been to grind it flush and drill it out, potentially a day's work. The studs screwing into a boiler are quite unusual. The thread into the seating is tapered and must be specially machined. However, by end of day, Tom, Cameron and Bob had substantially machined the new stud and, when I dropped by on Sunday, work was progressing. We should have it replaced ready to fit the cover next weekend.
· With the stud out, work focused on fitting the dome cover. This was the first time that we had used the new boom for the forklift, which was made with this type of lift in mind. It was highly successful. The cover was lifted by the forklift in the shop and placed fairly easily.
It was then tightened down without issue. This was a great deal easier than the previous method that required the locomotive to be pulled outside to use the boom truck to place the cover.
· Jason tested the remaining gauges, which all proved to be accurate, so these are now ready for refitting.
· Jane finished stripping the air tanks. These are now ready for painting.
· With Jim West's assistance we refilled the milk car so should now have a water supply sufficient to support testing under pressure. We have now run about 9000 gallons of water thru the boiler which should have removed most of the debris from sand blasting. From now on we should be able to re-circulate the water.
In other areas:
· Stu and Bob ran the wiring for the planer. The one remaining requirement is to locate a breaker to fit our old style supply panel.
· Dennis was rebuilding the damaged grease keeps for the axle boxes on #428.
So a lot was achieved this week. Hopefully next weekend we should be able to fit the inspection hatch and start testing under pressure.
Nigel
Friday, July 19. 2013
3rd Annual Benefit at Sanfilippo Estate Posted by Nigel Bennett
in Steam Department at
20:00
Comments (3) 3rd Annual Benefit at Sanfilippo Estate
Sunday 14th July was the third annual Steam Department
Benefit at the fabulous Sanfilippo Estate.
I believe that a wonderful time was had by all who attended. Certainly I took some friends who had not attended before and they all judged it one of the highlights of their year so far. The collection of antique music machines is beyond description and you could spend hours watching these alone.
The fairground organs and carousel are superb pieces.
The grand Wurlitzer organ is both spectacular to see and, when played by an organist of the caliber of Dave (Jeff's brother), provides an enthralling performance. Some of my more musical friends watched in complete fascination. Dave seems to become one with the instrument with both arms and legs in constant movement around the keyboards, stops and pedals.
A new addition this year was the showing of a Buster Keaton silent movie. It was fascinating to see the organ used for its original purpose, providing the sound for the showing.
Many thanks to the museum volunteers who assisted in running the event. With the exception of JD who was elsewhere at the time, they are shown here with Jeff and Dave on the locomotive in the carousel house.
Thanks again to Jeff for organizing the event, to his brother Dave for another outstanding performance and to the Sanfilippo Foundation for the access to their wonderful collection.
Nigel
|
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]