Sunday, May 22. 20112011 Mainline Tie Project
This
year, like most years, the museum’s Track Department undertakes a large
tie renewal job. This is a necessity to properly maintain our railroad
and allow for a high quality ride all of our visitors and volunteers
have come to expect. This year, it was decided to undertake one of the
largest tie renewal projects to date, nearly 750. Typical years may see
500 ties replaced anywhere on the property where they’re most needed.
This places a huge strain on us to complete the bulk of the work before
operations ramp up in April and May. Whether it’s the Mainline, Carline
or little used yard track the importance of maintaining our track for
the safety of the public, our volunteers, and the fragile equipment we
operate is always the top priority of the Track Department. Always…
So what does it take to get the job done? This process began last year with the purchase of the 750 brand new ties to be installed. All of which were delivered by truck and unloaded on the property. During this year’s detailed track inspection beginning in the cool month of March we walked up and down the railroad not only inspecting the track, but also marked bad ties to be replaced. Once a majority of the ties were marked for replacement we had to figure out the best way to get the new ties on site. This year, because of the huge quantity of ties, we found it best to load all of them onto a flatcar and roll them out to the site. With our Burro crane we unloaded all of the bundles in the general locations that would be needed. This is not an easy process and most of this work happened during the last half of February and into March. Needless to say there was plenty of ice and snow on the ground to make the job difficult. With the ties all on the ground, the lengthy process of placing each tie in the exact location where it was to be installed began. Mostly, this involved the tie crane and an operator working eight or nine hour days over the weekends. This step took many weekends throughout March and April to complete. While that was happening, we also moved new spikes in locations they could be accessed and continually worked on machine maintenance. Things break, machines wear out, and we spend a lot of time and elbow grease keeping the machines in running condition. With only our small core group of volunteers, and without the necessary equipment to do the actual replacement ourselves, we hired a railroad contractor to truck in their own equipment and swap the bad ties for the new ones. This took a solid week for the contractor to finish the job and then the cleanup of all the material was left to us. As with most tie projects, the work typically disturbs the track severe enough to require a slow order. The problem of support under the ties becomes an issue without being properly tamped. Until that happens, the ties may not have enough ballast underneath which could create an unsafe condition. At this point the race was on to clean up the railroad before the operating season gets into full swing. During this time all of the old ties were collected with the tie crane and placed in one large pile near Johnson Siding where they will eventually be picked up taken away by another railroad contractor. Just like when they were all set out, the job meant the tie crane and operator must spend long days peddling ties back and forth. This year it took us five or six full working days and detailed cleanup still isn’t finished. In addition to all of the ties, other material had to be picked up, such as old line poles and tree limbs. This adds considerable time and energy but needs to be done. With the wood picked up we focused on gathering all of the steel scrap which took the form of 2,800 spikes from the tie job, hundreds of old tie plates and other track material left on the line from years past. This could only have been done quickly and efficiently with our Burro crane and its electromagnet. We took one of our flatcars and ran up and down the line until the flatcar was full of steel and brought it back to the property to be sorted. That brings us to today. The next steps will be to get rid of our huge tie pile at Johnson Siding, and surface the railroad. Surfacing the railroad will be done in house using our ex Amtrak production tamper purchased a few years ago. Contracting an operation such as this would cost the museum another $40,000 and that does not include regulating the railroad afterward to finish the project! All of the work done in house by the Track Dept. easily cuts the total cost of the project in half and in this season alone has already saved the museum roughly $50,000. The alternative to any of what we do in house involves renting and trucking in equivalent machinery and paying contract wages. Work will continue throughout the season to tamp and dress the line working between operations and special events. Follow up maintenance on all of our machines and sorting materials from the line will take many more weekends of work. Without the equipment we have, most of this wouldn’t have been possible. While most of this work goes unseen to a majority of our volunteers and visitors, it is this work that is required for our museum to function as a world class operation. None of this could be done without the dedication of our Track Department working odd hours in all sorts of conditions. Thanks to all who have helped on this project including Frank DeVries, Tom Hunter, Bill Lygiros, Patrick Shea, Jeron Glander, Mitch O'Brien, Bob Olson and Adam Robillard. Also we must thank everyone who supported the work including, but not limited to, the Operating Department granting us track time, Dave Diamond in the Buildings & Grounds Department, and anyone I may have missed. …and that’s what it takes to get the job done More Track Dept. photos from Frank Devries and Adam Robillard can be found in the Member's Photo Site here- http://www.irm.org/gallery/Members-Photos Sunday, May 22. 2011Wood Shop Update - May 21, 2011This entry will be short since almost three hours of the day were spent with members of the OWWM group. That is short for Old Wood Working Machines. We are again hosting their annual meet - for the seventh consecutive year! We had few members of the planning committee on hand - from Wisconsin, Michigan, and Illinois and time was spent surveying the improvements and changes at IRM and planning some of the activities to be held in September. This is a loose knit informal organization, with website, that has visited us often, conducting clinics, demos, and any manner of other activities for 2.5 days each year. They have been very generous in helping to support our wood shop. If any of you guys are really interested in old such machinery, contact me for more information; but beware, any machine made after 1970 is considered TOO NEW! While we were walking around, we noticed some white lines painted on the grass near the Thomas Event entrance gate. This is the proposed new paving and construction for the west end Electric Trolley Bus loop. It will be exciting to see that take shape. But back to the Wood Shop - - - Victor Humphreys is shown "raising a panel" for the new station door. That is where the inserted panel in the door openings have a raised center field. The operation is called "raising the panel" although in practice it is the surrounding areas that are lowered. John Faulhaber and Victor worked on those tasks in the morning. Victor is checking the fit for two of the panels in the new door frame. These must be made to float or fit somewhat loosely in their grooves to account for seasonal expansion of the wood. We saw them for a fairly snug fit and then hand sand to fine tune for each opening. When all are in place, they will be inserted as the frame is glued and assembled. |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]