Sunday, March 16. 2014
Steam Department Update 03-15-2014 Posted by Nigel Bennett
in Steam Department at
11:07
Comments (2) Steam Department Update 03-15-2014
What a difference a week can make. The Winter still clings on - we left Saturday evening in falling snow and the shop water supply is still frozen. However, even a couple of days at near normal temperatures during the week has had a remarkable effect on the snow and ice around the museum.
For the first time in months, strange parallel lengths of steel have started to appear from the snow banks. The sound of a diesel locomotive was heard again as Jamie worked with the track gang to plough key lengths and start the Spring inspections. A lot catch up is required on track work delayed by the weather. Aside from the normal inspections, a large part of the steam collection is still out by the depot and cannot be moved back until work is completed on the track and switch leading to the steam lead.
On 1630 work continued steadily
One important effect of the thaw was that we were able to get to the box car and retrieve the dome cover. While this will not be fitted until the last minute when the locomotive is outside the shop, we urgently need to prepare it and spray it at the same time as the boiler so that the finish is the same. Thanks to Phil who grabbed the camera and provided a rare shot of Nigel actually doing something as opposed to standing behind the camera!.
People with paint brushes were all over and around #1630 and her tender. The walkways are now largely complete. The tender truck frames have been done and the sander lines were being touched up. Irregularly shaped parts like this generally take about three shots, paint one way up, turnover and paint the other side, then stand back and spot / touch up the small areas that somehow did not get painted in either of the previous shots!.
The tender wheels still need to be cleaned and painted but that is an area which will is seriously impacted by the loss of water supply, as these need to be pressure washed.
And an update from Jim on Sunday morning!. The pilot is now completely painted!.
We are getting close to the point where the large areas of sheet metal can be sprayed.
Dennis was hard at work welding the weak spots on the corners of the cab so that these can be finally prepared.
Large areas of the sheet metal have been rubbed down ready for spraying. After some thought, areas where bare metal has been exposed are being treated with sprayed primer. While the epoxy coating is self-priming, we are finding issues with the bare metal developing a rust tarnish when left exposed for a week and more. Since the area is far too large for us to rub down in one day, covering the areas we have done seems preferable.
In other areas:
Bob continued work to make the planer fully operational. He was working primarily on a pressure switch system that gives the operator an illuminated warning when the hydraulic system is pressurized. The picture below gives a much better idea of how this huge machine operates.
The massive “L” shaped cutter assembly can move vertically on the tower to the right of the moving bed.
At present the cutter assembly is relatively low. In this position, tools mounted on the horizontal arm of the cutter assembly would cut the top surface of the work, while the threaded shaft would advance the cutter horizontally after each movement of the bed.
The assembly can be raised substantially, allowing tools mounted on the vertical arm of the “L” to make a vertical surface on the work. Again a threaded shaft advances the cutter head after each pass.
I will now be travelling to the UK for a couple of weeks so will be watching progress with interest from a distance. Nigel
Thursday, March 13. 2014
Steam Department Update 03-08-2014 Posted by Nigel Bennett
in Steam Department at
17:48
Comments (0) Steam Department Update 03-08-2014
It was another day of steady progress in the Steam Shop.
The Winter continues to cause challenges that we have to work around. In the last week, we have lost the water supply to the shop. Thank Heavens we had largely completed what we needed to pressure wash. However, we will need a substantial water supply for equipment cleaning within a few weeks, as we spray paint the boiler and cab. So we monitor the thaw with great concern.
Some idea of the snow around the site –
On a separate issue, a number of people have expressed surprise that my name does not appear on the list of candidates for the upcoming museum board election. I have to admit that this was an error on my part in missing the deadline to return the acceptance of nomination form.
On 1630
Painting of the lower areas continued at a rapid pace.
The walkways on the fireman’s side were needle chipped, wire brushed and primed. Hopefully one of the team will be able to topcoat during the week, as this is an area that we use quite frequently. So it would be best for it to be finished and fully hardened before the weekend. In addition, as shown below much of the pilot is now in primer.
Collin, under guidance from Dennis, cut and ground out the last of the old steel mounting points for the spark arrestor from the smokebox. Phil and Brian then started test fitting the new steel assembly. Rather as expected, the first fitting into the final position indicated the need for a bit of adjustment by Dennis. However, the process has started.
In other areas:
Phil has been making major strides on clearing and freeing up working areas in the shop. Some of the results are spectacular for those of us who have been around a few years. The big old workbench on the East side, whose drawers have been unopened for years, has now been cleared and lubricated. It now provides work space and usable drawer storage!.
Work continued on the planer. It is now no longer second hand information. The huge table was moving back and forth smoothly for prolonged periods. The focus was on fixing leaks in the hydraulic system. Several have been fixed. Work continued on a couple that are proving difficult. This commonly means that the threaded union has suffered damage and must be replaced to get a good seal at the high operating pressure. Difficult to see how this could be on a machine that was only stripped down about 50 years ago and then left lying in pieces!.
But here it is. A last check by the proud team.
The huge table starts from the North end.
…. and surprising quickly it has completed the cutting stroke. It does not look much but the table is an enormous block of steel yet it moves smoothly and silently from end to end, stopping sharply at each end.
So, after 50 years it is substantially operational again. Well done guys!.
So steady progress continues for another week. Now if only the thaw continues!. Nigel
Sunday, March 2. 2014
Steam Department Update 03-01-2014 Posted by Nigel Bennett
in Steam Department at
11:50
Comments (4) Steam Department Update 03-01-2014
Oh well, we are into March. You would not have guessed it at Union yesterday as we gingerly picked our way across thickly ice encrusted roads to get between the shop and the amenity block. The day was then somewhat shortened by the development of a steady snow storm as darkness fell. However, there was a reasonable turn out and steady progress continued.
On 1630 it was very much “more of the same”, which is exactly what we need at this point.
Painting continued on the frames and running gear. Christian joined the team for the first time and, by afternoon, was fitted in between the frames and top coating the cylinder casting and adjacent areas. There is a lot of variety in the steam shop. As a new volunteer, you cannot be sure if you will be handling a paint brush or a 20 pound hammer!.
Meanwhile Jerry worked between the frames ahead of the firebox. So most of the lower areas of the locomotive have now received top coat and attention moved to the tender. Jim and Jerry painted most of the tender frames during the day. (The positioning of the bucket is unfortunate. Honest, we are not painting it with driveway sealer!!).
There are a few more weeks of work on the lower areas of locomotive and tender that will not be obvious unless you are standing next to the locomotive. A number of pipes and the under sides of the walkways need to be cleaned, primed and painted. In addition there is a major review and touch up exercise. Whenever you shine lights and look from different angles you spot areas that are not fully covered. So there will be a significant exercise of inspection, with a brush in hand, to touch up these spots and finish the job.
Dennis had welded some areas of the cab last week and identified further areas on the fireman’s side that needed grinding out and clamping so that he could weld. I cleaned these up so they are now ready for welding.
This weekend Dennis was cutting the new mesh sections for the smokebox spark arrestor.
Jason located another steam heat gauge, very similar to the existing one. He was able to exchange the face of this one with the damaged face of the existing gauge so we now have a good looking gauge to fit.
Rick removed the sander discharge pipes as these would be in the way of spraying the cladding sheets of the boiler. He then wire brushed these ready for painting.
On 428:
Ed worked on the sander manifolds. He showed me an interesting feature. The inspection plugs of the sand channels are filled with lead. Apparently this wears better under the force of steam driven sand than does iron or steel. One of the plugs needs a new lead filling.
Dennis and Phil worked on one of the brake rods.
In other areas, a major milestone was reached last week on the planer. I understand that, after much investigation and adjustment it is now effectively operational. Critically, it was adjusted so that it now moves on the cutting stroke at an adjustable speed and then returns for the next cut at a surprising speed for such a large machine. In addition, features that were not previously understood are now seen to operate. For example, a small hydraulic cylinder actually lifts the cutting head at the end of the cutting stroke so that it is positively lifted above the work as the table returns.
All of this is second hand from the team as the machine was not operating this weekend. A number of leaks were identified in operation so a couple of seals will be replaced and some connections remade to bring it to readiness for routine.
So a week of steady progress. Now what we need is the Spring!. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]