Sunday, June 24. 2012Steam Department Update 6-23-2012The dog days of summer continue. Many people have vacations or other better offers so turnout at the shop is lower than usual. I had to leave in the early afternoon so hopefully others things were achieved later in the day. Anyway, I think we turned a corner this weekend. We have just about completed the stripping and measuring and are now working on repair and rebuilding tasks. Work focused on 1630: · Jeff, Collin and I measured the radius profile of the back head to provide Bob the last data for the form 4 calculation. I need to finish a few more diagrams to identify exactly where measurements were made on each part of the boiler and Bob has a mass of calculations to complete and document but we now have all the physical measurements to complete the documentation; · the holes for riveting the patch into place have now all been prepared; · Jeff and Collin marked all the points where we need Dennis to make good small marks in the tube sheets before fitting the tubes; · The big exercise now getting under way is the repair and safe ending of the super heater flues o Phil sand blasted the material that will be cut to provide the safe ends; o all of the flues were inspected and those with an existing weld too close to the end were identified and cut to ensure that there will be an adequate length of clear tube at the end for expanding into the tube sheet; o each flue was marked up with the position into which it will be refitted (the spans vary a little so from here on all the measurements and amounts to be added will be specifically calculated to fit the tube to it chosen location); o a start was made on cutting the small diameter safe ends for some of the flues. Bob and Ed worked on reassembling and firing up the rivet furnace. It was test fired during the afternoon so hopefully we are now ready for riveting 428's cab. Glenn inspected and lubricated the boom hoist mechanism on the Bay City crane. As the most frequent operator of that crane I have a vested interest in this activity. The boom hoist has always been very tricky to engage and disengage smoothly so any improvement in this area will be a major benefit. Don't forget the Steam Department benefit next Sunday. You can still order tickets but will need to pick them up on the day. Nigel Sunday, June 17. 2012Steam Department Update 6-16-2012The weather had a significant effect on work this weekend. We had hoped to pull the Shay truck out and complete the steam cleaning but sharp thunder storms in the late morning meant that the wheel drop covers could not be removed to allow the shunt. 90 degree temperatures and high humidity made all heavy work pretty slow. However some significant progress was made on 1630. · Despite the heat, Phil spent most of the day in the boiler with Collin in the morning and Jason in the afternoon and completed the measuring of all the back head braces using the webcam and "fork" approach. Vince and I, outside the boiler recording the pictures, certainly had the easier end of the deal. However the results were well worth the effort. Having checked all braces it is now clear that all are the same size (1 3/8 inch diameter) so significantly stronger than the drawing shows. The end result is that we are now sure that the bracing of the back head is a good deal more substantial than previously thought based upon the Frisco drawings. · Kevin did a great job on the top of the tender. He has worked during the week as well on this and now has the whole top of the tank needle chipped. He is close to the point of final cleaning and being able to re-prime the metal ready for repainting. · the measuring of the exact distances between the tube sheets for each super heater flue was completed. This gives me my homework for the week. Now I can work out the exact lengths we need for safe ending each flue and we can then get down to cutting and fitting the ends to the flues. · We also continued the measurement of the back head. As with everything in this area, nothing is as simple as it first seems!. The critical measurement is the area of flat sheet facing into the cab. (The curved area where the sheet is flanged forward to join the side sheets does not require bracing). The initial calculation assumed the flange was of constant radius. Now we know it actually increases in radius as you come down the sides. What initially looked like school level geometry is looking more like college level maths !!. In other areas · the last bull ring for 428 is just about complete, which will free up the lathe to produce the new piston rod for the McCabe; · the honing of the connecting rod has reached an acceptable level of "roundness" in the rod ends so we were at last able to free up the pillar drill and the area around it; · the new numbers for 938 were completed and fitted to the front lamp so she now looks a little tidier. Nigel Sunday, June 10. 2012Steam Department Update 6-9-2012The high temperature and the number of visitors associated with the Union Pacific family day meant that work was a little more subdued than usual this weekend. However some significant progress was made. On 1630 the main focus was on investigating the back head braces. As discussed last week, the drawings, which have been the basis for previous calculations, suggest that this is the most highly stressed area of the boiler and potentially limits the pressure at which we can operate. For this reason we worked on ways of measuring how big the braces really are. This is no easy task as the critical braces are above the inner firebox 6 to 8 feet back between rows of stays that are only 4 inches apart. The picture shows the area braced. The position of the attachment bars is marked in chalk and, within these, the circles show the attachment points of the braces. The method developed relies upon using a rigid steel "fork" that is strong enough to break scale off the brace and marginally less that 1 3/8 inches across. This will just fail to pass over a 1 3/8 brace but would easily pass over the smaller 1 1/4 or 1 1/8 (the 3 sizes shown in the design). This was proved and tested on the front tube sheet braces, which are very similar but easily accessible. Most of the team supported Jeff and Phil to develop a rig of webcam and lighting that could be fitted between the stays to observe and record the fork being applied to braces hidden above the firebox. Whilst painfully slow and hard work for the guys, particularly given the heat, the results were very encouraging. The first two of the hidden braces we have reached are definitely NOT the smaller 1 1/4 size shown on the drawing but 1 3/8. So we can already say the bracing is stronger than drawings would suggest. The bad news is that the remaining six braces are even more tricky to get to!!. Phil made a second test fork shaped to give us the best chance of reaching these and we will continue next week. The shot above is the result of this process. This is about 7 feet along the length of the firebox but clearly shows the brace and the measuring fork. The fork would be an easy fit on a 1 1/4 bar and just fails to pass over a 1 3/8 rod, so this is clearly larger than the drawing shows. (In case anyone is wondering why a difference of 1/8th inch is so significant, the stress is related to the cross sectional area of the braces so the difference in area and reduction in stress between a 1 1/4 and 1 3/8 brace is a full 20%). Mike, Bob, Ed, Stu and others continued drilling out the rivet holes for the firebox patch. This is now approaching completion. All the holes are now pilot drilled and are being steadily increased in size to create the exact size required for the rivets. We received the steel bar needed to produce the piston rod for the McCabe and Bob set that up in the lathe to start the machining to produce the piston rod. Once the McCabe is repaired we can start work on the patch itself. Glenn repaired the Sullair so we are now ready to sand blast the tube and start work on the safe ending the super heater flues. Stu and Bob worked on assembling the hydraulic pump for the planer. This will be a powerful tool if we can bring it into service. The table moves back and forth thru the cutting head allowing several large items such as axle boxes to the machined consistently and simultaneously. Phil and I collected the new cab windows for 2050 that have been made in the woodwork shop. These are beautifully made and will really improve the look of this impressive locomotive. .............. Don't forget the Steam department benefit at Sanfillipo on July 1st tickets are available on the main web site. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]