Friday, September 13. 2013Wood Shop Update - September 11, 2013There are a lot of topics and pics this time around. I will lump most together in this entry, and make a following entry for the CGW X 38. The crew working on Cleveland Transit System 4223 has a nickname for everything. In this case there is no mistaking the formed metal head lining going into the front end of the PCC. It is not really that thin, so it is pretty heavy and required many hands. To lift it, hold it up, and take deep breathing exercises while some screws were driven into place. In case you did not recognize all the players in the first picture, here is another view of the crew on the clamshell job. Maybe this is the better side that you will be able to set names to. Nick Rindt set up some horses on the outside and scrubbed paint off of several of the metal panels that were used to hold ad cards. Al Reinschmidt came over to the shop near the middle of the afternoon and set about taking the above panels, wiping them down, and applying primer. John Mc Kelvey is working on another seat for the LAKE CITY. This bench seat is destined to go into the smoking lounge of the Men's Lavatory. John Faulhaber (shown) and Gerry Dettloff have spent a few extra days on campus this week. The result is a new piece of roof canvas in place on the Lake Shore Electric 810. This traction trailer has been a long time in the shop and now it appears the end may be near. The canvas has been stretched and tacks are being driven. Just across the aisle from the LSE 810 is our Michigan Electric 28. Jeff Brady and Norm Krentel have labored long and hard and here is the result. A new wood roof, sanded, painted, and ready to receive new canvas of its own. Jeff Brady was in the shop and had set up a buffing wheel to polish brass window lifts and other hardware for the ME 28. Another restored window for the ME 28 receives some attention from Jeff as he mounts the needed hardware on the sash.
Thursday, September 12. 2013
CGW X38 OPEN HOUSE Posted by Robert Kutella
in Chicago Great Western X 38 Russell Snow Plow at
06:27
Comment (1) CGW X38 OPEN HOUSEYou have to see it!! In conjunction with Museum Showcase Weekend we are holding an open house for our Chicago Great Western X 38 Russell snowplow. This has been on site less than two years yet an amazing amount of work has been done. We have manufactured and installed eleven new windows, two doors, and relined most of the interior wood siding in the rear box of the plow body. Most of the cab cupola has been restored and that includes a newly restored and upholstered operators seat. Many body repairs have been done and the south side and rear end are completely repainted and lettered. Most of the remaining body is quickly being restored and repainted. Air piping has been repaired and is working. Last year we did much this same thing to the delight of many of our visitors. So stop by Track 40 from 1-2 PM and look over the progress. We will also include the opportunity to climb into the car and up into the cab. Plan on staying there a minute and taking a turn at the controls to be able to personally operate one of the plow wings! This will require physical ability to climb steps and a ladder and there are cramped spaces and a potential headknocker. We will have a donation jar on hand so please fill it with greenbacks to help the work continue. Come help us celebrate the 77th birthday of this plow.
Sunday, September 8. 2013
Steam Department Update 09-07-2013 Posted by Nigel Bennett
in Steam Department at
19:42
Comments (8) Steam Department Update 09-07-2013
It is good to be on the home straight with 1630 but it is increasingly clear that there is still a lot of work to do!. Also some of it is pretty slow and tedious.
It has been a huge benefit to have Brian Davies on site for the last three weeks and a great deal has been achieved in that time. Things will move a lot more slowly when he returns to Florida on Monday.
When I arrived on Saturday it was spectacular to see most of the steam collection in the open air, having been switched out of barn 9 for the filming of the Transformers 4.
On 1630 the has been a lot of progress. The two major areas of activity have been finalizing the fitting of tubes (as a prerequisite to installing the super heater elements) and fitting lagging to allow installation of controls and air tanks that must be in place to allow testing.
· During the week Brian Davies had put in a lot of hours and had completed the beading of all tubes in the rear tube sheet;
· On Saturday teams of us took it in turns to prosser the tube ends in the rear tube sheet. This process involves expanding the tube slightly on the water side of the tube sheet, using a multi-segment expander driven by an air hammer. The effect of slightly expanding the tube on the water side is to firmly lock the tube into the sheet between the bead and the slight expansion caused by prossering. Anyway, it is a two man job and, by several teams taking it in turns, all 200 tubes were completed by late afternoon. The boiler was then refilled and we started to heat the water. The objective on Sunday will be to test the tube ends under operating pressure and tighten any that show leaks as a result of the beading and prossering. As soon as we are satisfied that the tube ends are dry, the tubing exercise is complete. The motor can then be removed from the smoke box and installation of the super heater elements can begin. So I wait with some trepidation to see if this can be achieved on Sunday !.
· Stu and Bob worked with Tom to set up a mounting that will allow the throttle to be rigidly located for machining and lapping. The surfaces of the throttle valve need to be leveled and ground to a tight fit that will provide a good seal before the throttle is refitted. By end of day the throttle was mounted and ready for work to be done.
· Dennis started on the plate work and mesh that fits around the blast pipe. He has now assessed all the pieces and identified what new material will need to be fitted to complete this structure once the blast pipe is in place and the super heater elements tested.
· The lagging is proving rather more troublesome. Two areas are critical for the steam test, the firebox in the cab (to allow fitting of numerous pipes, valves and gauges that are required both for steam testing and pressure testing of the super heater elements) and the first couple of sections of the barrel at the front (to allow refitting of the large air tanks required to complete the air system).
· Work started on fitting the barrel lagging at the front. This is not as simple as it looks (and it does not even look that simple !). The insulation is rigid blocks that cannot be conformed to the curvature of the barrel. So it must be cut into strips about 12 inches wide and the edges cut at an angle so that adjacent blocks fit tightly together along their length. However the blocks must also be tapered along their length. The boiler is formed of 3/4 inch plate in overlapping sections. So, in order to get a smooth taper over which the sheet metal can be fitted, the 2 1/2 inch insulation must be tapered along its length. (Basically the last section at the rear of one boiler ring is the full 2 1/2 inches thick while the front section on the next ring to the rear is 1 3/4 inches thick so that the insulation runs smoothly over the 3/4 inch transition in the boiler plates). Then, having cut sections of insulation to the correct taper along its length and sides, each must be cut around any pipes, hand rails or other projections to fit a specific location. The block is then wired to the wire rings that were placed around the barrel some weeks ago until a complete circle is achieved around the boiler. This will then be strapped into place and the sheet metal fitted over it.
· The sheet metal provided a bit of a setback. Jane had done a lot of work to ensure that all the metal had been cleaned and primed ready for use and had actually been short of painting work in the last couple of weeks once this was done. When we tried to locate the first major sheets required for the front ring they could not be found .............. until we found a whole lot of 1630 sheet metal that had been stored behind a few sheets belonging to #26 !!. It had been overlooked for cleaning and painting so Jerry spent much of the evening wire brushing a lot of sheets and I started painting the ones we need most urgently ..... oh bleep !.
· However the real nightmare is the cab. The sheets covering the top and sides of the firebox in the cab overlap and hold down the curved sections that cover the transition between wrapper and backhead. These, in turn, secure the sheets covering the backhead. The arch of sheet metal running up the sides and across the top of the firebox in the cab must first be located so that the curved sections can be located under its edge. The critical element of the arch is that two pieces of sheet metal must be worked up into the maze of pipes and valves around the turret and linked with 3/8th threaded rods either side of the turret. In addition, insulation must be set under this area in the form of small cut blocks or mud. Once the link is made the sheets form a complete arch that is tensioned by other threaded rods secured into the footplate. All jolly good fun as the area into which the metal and insulation must be placed can only be reached at arms' length from the narrow space at the sides of the firebox or by lying on the cab roof and reaching down several feet into a nest of pipes.
o Most of the work in this area on Saturday was planning to determine in which order pieces can best be fitted. This is critical to the project as the controls essential to testing for leakage in the super heaters cannot be fitted until this is done.
o The sheet metal either side of the firebox is in place to provide protection to the insulation already installed.
o David finished cleaning the fire hole door and I chased the threads on the mounting studs so this can be fitted as soon as the tube ends in the fire box have been proved tight. This is important as much of the backhead lagging is based upon the fire hole door casting.
In other areas
within the shop:
·
Phil and Cameron
worked with Tom on machining the bolster for the Shay;
·
Dennis started the
long process of building up the axle boxes for 428;
·
Stu and Bob achieved
a major milestone on the planer. The
power is now connected and both motors were tested. The head can now be raised and lowered
correctly and the motor driving the hydraulic pump now operates. The next big challenge is how to remove
decades of muck from the drain area under the bed. Since the lubricant supply to the table is
collected and returned to the pump thru this area, there is a considerable
incentive to get it as clean as possible before we try circulating oil thru the
system.
So, a lot of work
done but still a good deal more needed to get to the steam test.
Nigel
|
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]