![]() |
![]() |
Sunday, December 22. 2013
Steam Department Update 12-21-2013 Posted by Nigel Bennett
in Steam Department at
12:08
Comments (4) Steam Department Update 12-21-2013
This Winter is becoming a bad joke !. Today was the official start of Winter but we have been in the deep freeze for several weeks. Amazing to look back and see that this time last year we were working outside on the KCS tender that had recently been unloaded. This year we had a crew much reduced by a forecast of a substantial ice storm reaching Union in the afternoon. In practice, although the forecast caused several people to leave in the early afternoon, the air temperature held up better than forecast and the last of us were not driven out until 7, when the rain started to freeze on the cars.
Setting foot outside the shop was an adventure all day as the ground was well below freezing and any unsalted areas were simply sheets of ice which built up further as the rain fell.
However, in the shop we were able to progress steadily.
On 1630:
On the Shay, Phil and I worked with Tom to plan the next
steps on refitting the front truck. Six
large bolts need to be acquired and fitted to secure the casting in which the bolster
of the truck pivots. The holes for these
need to be reamed to allow the long bolts to be fitted. Phil will caulk the rivets that were placed
several years ago so that Dennis can go
ahead with refitting the smokebox bottom sheet.
Elsewhere in the shop:
So more steady progress despite the weather.
Nigel
Sunday, December 15. 2013
Steam Department Update 12-14-2013 Posted by Nigel Bennett
in Steam Department at
14:08
Comments (0) Steam Department Update 12-14-2013
The weather this weekend certainly had a major impact. Steady snow in the morning made me very doubtful about the long drive out of Chicago but, after a rather slow and slushy drive, it became apparent that the forecast was correct and the snow was less to the West, around Union, than it was in the city.
It was a very select crew, aside from myself, only Phil, Jane, Ed and Jerry made it to the shop. However, we managed to get a number of jobs done on 1630. But first, Phil made sure that the traditional Steam Department decorations were in place.
Merry Christmas from all at the Steam Department
Jerry has been working steadily on the insulation during the week and continued Saturday. The sheet metal is now re-installed along the boiler, after the work that was done to fix the steam leak, and the steps and pipework are back in place. This area is now ready for painting before the banding can be reinstalled. In addition he has now largely completed the firebox sides. The engineer’s side is complete and in place. The fireman’s side is complete aside from one piece of sheet metal that is set aside to serve as a test piece for the painting.
I hydro tested the equalizer tank, which tested at 150 psi with no issue aside from slight leakage from the small brass water drain cock. That was lapped and re-installed so the tank is now complete.
Feeling like suckers for punishment, Phil, Jerry and I then set about re-installing it !. After a couple of hours of crawling under and into the loco and much cursing it was back in place. The parentage of whoever thought of locating this tank in among all the pipework under the cab floor was questioned many times !. The tank is not particularly heavy – maybe 40 pounds. However it has to be squeezed thru a hole on the back of the frame on the fireman’s side, turned thru 90 degrees and then moved over to its location on the engineer’s side by reaching thru holes in the plate work of the frame. Having done that, you then use timbers and hands, at considerable risk of getting squeezed, to lift and position it so that the threaded ends of the ½ inch securing rods can be coaxed into holes in the frame plate and nuts attached. The end result of all that effort would not be noticeable to the average person standing by the locomotive. But it is there!. (The small shiny object the end of which you can just see hidden behind all the pipework).
Jane made considerable progress on painting. The cylinder and valve end covers are now primed on the inside and ready to refit. The area around the reservoir for the reverser was cleaned and primed. The objective is to get this painted so that the tank, which needs to be refitted urgently so that the valves can be moved, will not need to be removed again.
Ed started work on removing the pipe leading to the water column. This is the last of the large copper pipes that needs to be annealed and re-lagged.
So steady progress despite the weather.
Nigel
Sunday, December 8. 2013
Steam Department Update 12-07-2013 Posted by Nigel Bennett
in Steam Department at
15:03
Comments (7) Steam Department Update 12-07-2013It was a good day for working inside the shop !. Temperatures outside discouraged anything but
limited activity. On 1630 steady progress was made on the work list: ·
Rick completed screwing the sheet metal section
around the radius of the backhead. He
has now moved on to making and fitting some additional sheet metal against the
front sheet of the cab, where there was a gap that exposed some insulation; ·
I removed the injector overflow (coal and
footplate spray hose), which was leaking dangerously during test running. The fittings have all been cleaned and
refitted. All we now need is a length of
new hose; ·
Ralph managed to remove the steam line to the blower,
remade the joint that was noted as leaking under steam pressure, then refitted
the whole assembly. So that issue should
now be fixed; ·
Collin and Ralph then removed the two injector
steam lines. These are large copper
pipes that need to be annealed periodically.
So we will do this and then renew the insulation that is wrapped around
them; ·
Jerry worked on the insulation along the
boiler. This is a slow and tricky job as
we need to close all the small gaps in the sheet metal that could allow water
to get in when the loco is outside in heavy rain. He has made good progress on making the
firebox sided cladding sheets, where the insulation is attached to the sheet
metal. In this shot you can also see
where the injector steam pipes were removed.
This also clearly shows the reason for different way of lagging this
area. The exposed heads, that can be
seen where the cladding is still missing, are rigid stays with tell-tale
holes. These must be checked annually,
hence the need to remove the sheet metal and lagging frequently.
He also located and test fitted some
special strips of banding that close the gap against the front sheet of the
cab. We had wondered why we had such a
large gap there until he found the missing strips !!; ·
Phil, with Evelina and Eddie, spent a dirty and
unpleasant morning in the firebox. They
managed to match the fire bricks to the gaps between the arch tubes, where they
form the brick arch, and produce a diagram that tells us exactly how many
bricks of each of the 5 types we need to build the arch; ·
We then made a cold trip to the service box car
and found the spares we needed to have a complete set in the firebox ready to
build the arch. Phil and I then checked
the Milwaukee box car out in yard 13.
This confirmed that we have large stocks of 4 types of brick (which came
from Eagle Pitcher in the 1970’s) but need to make a pattern for the smallest
ones which fit over the arch tubes against the tube sheet; ·
Jane painted the straps that secure the air
tanks. Phil and I set up the cylinder
front covers ready for her to paint so that these will be ready for fitting
once Tom has completed measurement of the valve chambers; ·
Evelina worked with Dennis on wire brushing the
tender coal space so that he can weld some strengthening steel in weak spots around
the stoker motor; ·
I reassembled the hydro test pump with the new high
pressure hose so that the equalizing reservoir can be tested next weekend.. On the Shay ·
Phil worked with Dennis on fitting the last of
the spring locating plugs into the bolster; ·
Ralph and I relocated all the components of the drive
shaft onto a pallet under the locomotive and I started to degrease these ready
for refitting; On 428 ·
Cameron completed machining the wedges; ·
One of the axles was hoisted so that accurate
measurements of diameter could be obtained.
This proved very satisfactory.
The tires have ample thickness to allow them to be re-profiled. Around the shop ·
Jane made good progress in stripping old paint
from the large press in preparation for painting; ·
Bob continued testing the planer. So a typical and productive Winter workday in the steam
shop. |
Blog AdministrationCategory TreeCalendar
QuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]