Sunday, June 9. 2013
Steam Department Update 06-08-2013 Posted by Nigel Bennett
in Steam Department at
17:38
Comments (5) Steam Department Update 06-08-2013I guess we would have to say that it was a reasonable rather than a good day of progress in the steam shop. While we moved forward with the critical activity that we have been planning for several weeks, progress was not as good as we had hoped. There was however real progress on the most critical work remaining to be done. Obviously the main focus remains on 1630 · Eric and Curt worked steadily at grinding the tube ends in the front tube sheet. This is a tedious job, requiring care to ensure that the projection is reduced to 1/4 inch but no less. They have now completed all but one of the super heater flues. Good work guys!. · Brian and David worked with Richard to install the wires to secure the insulation. Wiring of the barrel is now largely complete. · Jane worked on cleaning and priming the small cladding plates. These are used under the large sheets to seal around pipes and rods. Given the number of projections from the boiler, there are a LOT of these, all of which need to be clean and painted ready for fitting. · The remaining large cladding sheets were lifted back onto the top of the machine shop to store until required. · All of which brings us to the main event !. Work started on installing the rivets to finally secure the patch into the firebox corner and so complete the boiler shell. Firstly a correction to last week, which demonstrates the dangers of documenting things that happen while you are not there !. Having read last week's notes, Jerry pointed out that it was he, not Mike and Tom, who set up the timber staging to hold the bucker in the firebox. He even spent much of Memorial Day doing so. Sorry Jerry, my bad. Overall there are 13 rivets to be installed. Of these 6 are not significantly countersunk into the sheets and have conical heads on the outside while 7 (those in and closest to the corner) are substantially countersunk (and have shallow rounded heads on the outside). 11 are ready to install while 2 more require some further welding work by Dennis (after the 11 are in) before they can be fitted. (To avoid confusion, the six domed heads already in place in the corner are not rivets but patch screws threaded into the mud ring.) Bolts were set into each of the holes to lock everything rigidly in place before setting the rivets. One bolt is removed at a time and replaced with a rivet. In this shot the first rivet has been fitted in the front sheet while bolts indicate the 12 remaining to be fitted.
Work started on the cone headed rivets, of which there are four in the front and two in the side. Here two are fitted and the hole is ready for the third to be fitted. The heated rivet is passed to the team in the firebox and placed into its hole. The end projects substantially thru the outer sheet. The bucker is positioned behind it and activated to start hammering. In this shot you can see the length of rivet that initially projects thru the sheet. The hammer is carefully positioned on the projecting end. Hammering compresses the hot rivet to form the head. The time to do this is a matter of a few seconds as the contact with the mud ring and hammer cools the rivet very quickly, As the rivet cools from the light yellow, at which it is placed, toward a dark yellow and then red it cannot be further shaped by hammering. When the hammer is removed we can see the formed rivet head, still red hot. Forming the head of the rivet is rather like forcing back on a projecting cylinder of putty to form the required shape. The challenge is that it must be driven back accurately so that the head remains centered on the shaft of the rivet. If it once starts to bend, the force of the hammering will tend to accelerate the bending, resulting in a head offset from the body of the rivet that must be removed and replaced. The four in the front sheet went in well with no failures. Unfortunately the two in the side proved more problematic. The first did bend in forming and produced an unacceptable result. The head was ground off and, with a significant amount of work using the air hammers, was driven out, much to our relief as the greater concern is that it "mushrooms" in the hole and must be drilled out. This hole will need to be cleaned up during the week before another rivet can be fitted. Installation of the second rivet was attempted twice late in the evening. In both cases we had problems with the air hammer forming the head, as a result of which the process was stopped before the rivet was seriously deformed. So there should not be much problem in removing the rivet. The problems with the hammer were resolved but, by 9:30 at night, operator exhaustion was a substantial risk factor and work was stopped for the day. So nearly 1/3rd of the total are installed. The disappointment is that, based upon initial progress, we had hoped that substantially more would have been completed. So - to be continued next week. The other big exercise was the continuation of work with a large B&G team to relocate the materials from West of the shop access road. The tricky items such as the tank and cab of the 0-4-0 were safely located to a much better area, where they are now standing on more secure supports that will keep them clear of the ground.
So we will be back next Saturday with the target of making a good deal more progress with the riveting. Nigel Sunday, June 9. 2013
CGW X38 Update - June 8, 2013 Posted by Robert Kutella
in Chicago Great Western X 38 Russell Snow Plow at
10:51
Comments (0) CGW X38 Update - June 8, 2013The old TV commercial seemed to say "Parts is Parts", at least for a chicken. Not so true for restoration work. Bill Peterson is cleaning up many of the cupola window hardware parts. Earlier he had completed the fitting and installation of the floor repair pieces inside the rear compartment, left side. Victor Humphreys is installing a very old mortise lock for one of the doors on the snowplow. Lots of drilling, fitting, chiseling. Buzz Morisette continues the tricky work of restoring the window framing and sills in the cupola. Here he adding some paint to the framing for the left rear window. First thing in the morning Victor Humphreys went up on the roof and finished the second coat of new paint on the cupola roof, before the metal work got too hot in the sun. Uncertain weather drew out this task, but we are off and running now. We also applied the first maroon to be seen on the cupola. This to the posts, trim, and framing exterior, while Buzz applies some finish grey to the new wood sills and posts on the left side. Sunday, June 9. 2013Wood Shop Update - June 8, 2013Ray Piesciuk posted earlier about the good news for CTA 2153/2154. It is TRUE - here 2154 pokes its nose out of Barn 4 while Dave Fullarton is fussing below the car. Mate 2153 is inside over the pit. Note the trolley pole installed on the roof of 2154 to allow this normally third rail only car to operate on our railway. Dave Fullarton is engaged in restoring part of a trolley base to be used on our elevated cars. Disassemble (not always easy), needle scale away old paint, grease, and rust, sandblast for final cleanup, and then you may START the painting. The interior of Cleveland Transit System 4223 is undergoing a transformation at almost warp speed. Lorne Tweed and Eric Lorenz busily drill holes, tap for screws, and anchor the new parts in place. That would be post caps, panels below the standee windows, and the rail above them. Eric has restored one of the many bulls eye light fixtures that will be mounted in the ceiling of 4223. Not a trivial task for one of these but for 31?? Nevertheless this first one is absolutely perfect, better than new to my eye. John Mc Kelvey makes this job look easy but I would not want to tackle it. Here he is reupholstering a nice chair destined for the LAKE CITY. He previously stripped it down, cleaned and refinished the wood parts, and is now applying this appropriate period fabric. You need to see it in person - VERY NICE WORK! Many of you have probably heard that we hosted the Union Pacific Family Days picnic and outing for Chicago Service Unit employees and families. Lots of equipment was brought by UP for display and this is a view of the three car passenger train departing east from Station Track 2 behind C&NW heritage painted SD 70.
|
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]