Tuesday, March 22. 2016
Steam Department Update February / ... Posted by Nigel Bennett
in Steam Department at
11:54
Comments (6) Steam Department Update February / Early March 2016
Another month of steady progress in the steam shop. There is rather less detail this month as I was away for three weekends visiting family in the UK.
Obviously the central focus is on getting #1630 complete in time for the start of operations in May. The regular work for the annual inspection continues in parallel with the major project of the valve overhaul.
The boiler and other work for the annual inspection is now largely done. A couple of weeks back, Phil cleaned and checked the arch tubes. After that the last of the wash out plugs were re-installed. Yesterday the testing of the pressure gauges was carried out so these can now be re-installed. The boiler will then have everything in place for the hydro-test.
We will now schedule this test with the FRA inspector. Once this is done we can conduct the internal inspection and, subject to any issues detected in testing, plan on steaming.
Obviously one essential part of the annual inspection is correcting those items that are considered out of or close to allowable tolerance. In this context, the spring loaded buffer on the front of the tender is was overhauled and the upper cross head bearing on the fireman’s side is being re-metaled.
The buffer has been cleaned, spacers made to take up the slack in the springs and painted. Yesterday it was re-installed onto the tender.
The tender is now complete and all that remains is to re-couple it to the locomotive by refitting the main drawbar. This has been removed, thoroughly cleaned and inspected for any cracks as required for the annual. Recoupling will be done as we prepare for steaming as this is best done by pulling the tender out of the shop and lifting the drawbar into place outside, where we have space to use the fork-lift.
A big job completed recently was casting the new Babbitt bearing for the crosshead. What does this mean?. Babbitt (alloys of tin or lead with copper and antimony) has been used for nearly 200 years to create a bearing surface against steel or iron. A favorable combination of relative softness, compression resistance and porosity, which facilitates the distribution of lubrication, mean that it is widely used for bearing surfaces to this day.
However, while modern usage is usually as a thin layer in a backing shell of a harder material, the more traditional usage made use of another property, low melting point. The metal melts around 400-500 degrees and casts well at 800-900 degrees. It will adhere well to iron or steel that is treated with a flux but not to a dirty surface. The principle is then simple. One iron or steel surface, normally a casting, does not need to be machined and is over-size versus the shaft or rod that moves against it. Molten Babbitt is then poured into the over-sized space in which it solidifies to form the bearing surface.
In the most basic form, the bearing is cast in situ. A smoky flame is used to soot the surface against which the bearing will slide, any gaps thru which the molten metal could escape are blocked and the molten metal is poured in. The contraction of the Babbitt as it cools provides a small clearance and the bearing should be ready to go with no machining necessary.
The bearing that we must replace is that in the top of the crosshead which bears on the slide bar. In theory this could be cast in place. However it was felt to be considerably safer and more accurate to cast the Babbitt in the crosshead shoe with some excess and then machine it to final size on the planer.
To do this the shoe, with a tray positioned in the center to make the “U” shaped channel, forms the mold.
The whole assembly is heated in the furnace so that the Babbitt remains liquid when it is poured into the mold. The shoe is tinned to help the Babbitt to adhere while the tray is soot coated to help it release after cooling.
Once the babbit had completely cooled, the tray was removed, the crosshead shoe was mounted onto the planer and Tom has started machining the babbit to its final dimensions.
Meanwhile the valve overhaul has progressed well.
Both valve chambers are now bored to size and the boring rig has been removed.
The valve rods were sent out to a specialist for surfacing to remove areas of wear that form over time as they run in the gland packing. These are now back and ready to start the reassembly of the valves.
The four cast iron blanks to make the new bull rings have now been machined to final internal and outside diameters. Needless to say, each of the spiders proved to be of slightly different diameters, so each of the blanks is now unique to one particular spider and therefore one of the four positions in the locomotive. They have also been tested in the bores and proved to be the required fit on the external diameter.
These are now off-site being machined to produce the finished bull rings.
Many happy hours have been spent in cleaning the spiders and valve bodies. It is essential to remove the hard carbon built up on these but, each has a small lip that secures the spring ring. So it is a long and careful process to carefully remove the carbon without causing wear to the lip.
In preparation for re-assembly the studs that hold the cylinder ends have been inspected and around 50%, that were excessively corroded, have been replaced. This provided interesting confirmation of the history of #1630. On the engineer’s side 15 of the total 20 required replacement but on the fireman’s side only 4 needed replacement. This is explained but the fact that, in the late 1930’s, she was involved in a head on collision with a Mikado, suffered heavy front end damage, and the FS cylinder casting was replaced. So the casting and studs on the ES are mostly 20 years older than those on the FS.
A minor set-back has been the conclusion that the bores need to be honed before the valves can be refitted. As with many things in the steam shop, this needs unusual equipment. Honing a 12inch cylinder requires a pretty slow turning motor. While we have such a motor, it has not been used in many years and proved to need overhaul before it could be used. That is nearly complete so the honing can hopefully be done soon.
Once this is done and the bull rings are completed, we should be able to start re-assembly of the valves.
Meanwhile work has progressed slowly but steadily on the Shay.
Work has continued steadily on the cab for #428. The riveting team have been making good a few final missing rivets. Dennis has been filling holes and shaping the roof to remove a few non-standard curves that it had developed and John has been painting and fitting the window guides.
In the shop.
So a lot of progress but still quite a lot to do for the start of the season. Watch this space.
Nigel
|
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]